The honest, line-by-line breakdown of what it costs to build an ADU in LA County in 2026 — from permit fees and plans to framing, finishes, and utility connections. No lowball estimates. No surprises.

February 2026 12 min read|By Skyline Builders CA Inc.

1. The Bottom Line Up Front

A typical 600 sq ft detached ADU in Los Angeles County costs between $147,000 and $231,000 all-in — from the first permit application to the day you hand over the keys. That range is wide because LA is a wide market: labor costs in Bel Air are not the same as in Gardena, and a hillside lot with a retaining wall is a fundamentally different project than a flat lot in Torrance.

What this article gives you is a real, line-by-line breakdown of where that money goes — not the $80K fantasy numbers you see in some contractor ads, and not the $400K horror stories from people who hired the wrong team. This is what a transparent, well-managed ADU project actually costs in 2026.

Garage Conversion

$60K $110K

Existing structure, limited permits

Attached ADU

$90K $160K

Shares walls, combined utilities

Detached ADU

$147K $231K

600 sq ft, full new construction

2-Story Detached

$200K $320K

800–1,200 sq ft, premium finishes

The $80K ADU does not exist in Los Angeles. If a contractor quotes you $80,000 for a new detached ADU, they are either excluding permits and plans, planning to use non-union labor without proper insurance, or they will hit you with change orders once the foundation is poured. Budget honestly from the start.

2. Cost by ADU Type

The type of ADU you build is the single biggest driver of total cost. Garage conversions are cheapest because the structure already exists. Detached new construction is most expensive because you are building a complete home from scratch — foundation, framing, roofing, all utilities.

ADU TypeTypical SizeCost RangeKey Cost Driver
Garage Conversion400–600 sq ft$60,000 – $110,000Insulation, electrical, HVAC, bathroom addition
Basement Conversion500–800 sq ft$75,000 – $130,000Egress windows, waterproofing, HVAC
Attached ADU400–800 sq ft$90,000 – $160,000Shared wall framing, separate entrance, utilities
Detached ADU (1-story)400–800 sq ft$120,000 – $200,000Full foundation, framing, roofing, all utilities
Detached ADU (2-story)800–1,200 sq ft$200,000 – $320,000Structural engineering, staircase, larger footprint
Junior ADU (JADU)Up to 500 sq ft$30,000 – $75,000Interior conversion only, shared utilities allowed
Junior ADUs (JADUs) are the most affordable option — they convert existing interior space (like a bedroom or den) into a self-contained unit with a kitchenette. LA County allows JADUs up to 500 sq ft with no additional parking requirement and minimal permit fees. If your home has a spare room, a JADU may be the fastest path to rental income.

3. Full Cost Breakdown: 600 sq ft Detached ADU

The table below reflects actual costs for a standard 600 sq ft detached ADU on a flat lot in LA County in 2026. These are not national averages — they are sourced from real LA County permit records, local supplier pricing, and Skyline Builders project data.

Cost CategoryLow EstimateHigh EstimateNotes
Architectural Plans & Design$6,000$10,000Includes structural drawings
Permit Fees (LA County)$5,000$8,000Varies by jurisdiction
Soils Report / Geotechnical$1,500$3,500Required on hillside lots
Foundation$12,000$22,000Slab vs. raised foundation
Framing & Structural$18,000$28,000Lumber, labor, hardware
Roofing$8,000$14,000Composition shingle standard
Exterior (Stucco/Siding/Windows)$12,000$20,000Matching existing home style
Electrical (Panel + Wiring)$8,000$14,000200A sub-panel typical
Plumbing (Rough + Finish)$10,000$16,000Full bath + kitchen
HVAC (Mini-Split System)$5,000$9,000Per zone, energy efficient
Insulation$3,000$5,000Title 24 compliance required
Drywall & Texture$5,000$8,000Includes tape, mud, paint
Flooring$4,000$8,000LVP standard, tile in wet areas
Kitchen (Cabinets + Counters + Appliances)$8,000$18,000See Section 6 for detail
Bathroom (Tile + Fixtures + Vanity)$5,000$10,000See Section 6 for detail
Utility Connections (Water/Sewer/Gas)$8,000$18,000See Section 7 for detail
Landscaping & Site Work$3,000$8,000Grading, drainage, walkway
Contingency (10%)$12,150$19,950Always budget this
TOTAL$133,650$219,450600 sq ft detached ADU, flat lot
Hillside lots add $20,000–$60,000. If your property has a slope, you will need a geotechnical report, engineered retaining walls, and possibly a caisson foundation. Always disclose lot conditions to your contractor before accepting any bid — a flat-lot price on a hillside project is a recipe for a lawsuit.

4. Plans & Permits: The Real $13,000 Number

One of the most common ways homeowners get surprised is by underestimating the cost of plans and permits. Many contractors quote construction costs only — then the client discovers they owe another $10,000–$15,000 before a single nail is driven.

For a standard 600 sq ft detached ADU in LA County, expect to spend approximately $13,000 on plans and permits. Here is where that money goes:

ItemTypical CostWho Charges It
Architectural drawings (floor plan, elevations, sections)$4,000 – $7,000Architect or designer
Structural engineering calculations & stamp$1,500 – $3,000Licensed structural engineer
Title 24 energy compliance report$500 – $1,000Energy consultant
LA County building permit$2,500 – $5,000LA County DRP or city
School fees (LA Unified)$1,500 – $3,000LAUSD (charged per sq ft)
Fire department review$300 – $600LA County Fire
Plan check (first submission)Included in permit feeBuilding department
Plan check corrections (if required)$0 – $1,500Architect revision time
LA County vs. City of LA: If your property is in an unincorporated area of LA County (served by LA County DRP), the permitting process is different from properties in the City of Los Angeles (served by LADBS). City of LA has its own ADU ordinance and fee schedule. Always confirm which jurisdiction your parcel falls under before budgeting — it affects both cost and timeline.

Plan check timelines in LA County currently run 8–14 weeks for over-the-counter review and up to 6 months for projects requiring discretionary approval. Skyline Builders submits complete, code-compliant packages on the first attempt, which eliminates costly correction cycles and keeps your project on schedule.

5. Construction Costs: What You're Actually Paying For

Construction costs in Los Angeles are among the highest in the nation. Prevailing wage rates, high insurance costs, and the complexity of building on infill lots all push prices up. Here is what drives the numbers:

TradeLA Hourly Rate (2026)Typical Hours for 600 sq ft ADUEstimated Labor Cost
Framing carpenter$75 – $95/hr160–200 hrs$12,000 – $19,000
Electrician (journeyman)$90 – $115/hr80–120 hrs$7,200 – $13,800
Plumber (journeyman)$95 – $120/hr80–100 hrs$7,600 – $12,000
HVAC technician$85 – $110/hr40–60 hrs$3,400 – $6,600
Tile setter$70 – $90/hr40–60 hrs$2,800 – $5,400
Painter$55 – $75/hr60–80 hrs$3,300 – $6,000

These are licensed, insured, W-2 employee rates — not day labor. Any contractor quoting significantly below these rates is either using unlicensed workers (which voids your homeowner's insurance and exposes you to liability) or they are planning to cut corners on materials.

Skyline Builders uses in-house crews, not subcontractors. This means no markup on labor, consistent quality control, and a single point of accountability for your entire project. When something needs to be fixed, we fix it — no finger-pointing between subs.

6. Kitchen & Bathroom: The Detail That Matters

Kitchen and bathroom finishes are where ADU budgets vary most dramatically — and where the biggest gap between a "rental-grade" and "premium" finish lives. Here is a realistic breakdown for both a budget-conscious and a premium finish level:

Kitchen

ItemBudget (Rental Grade)Premium
Prefab cabinets (Home Depot / IKEA)$2,500 – $3,500$6,000 – $12,000 (custom)
Quartz countertop (installed)$1,800 – $2,800$4,000 – $7,000
Cabinet assembly & installation labor$2,500 – $3,000$3,500 – $5,000
Appliances (range, dishwasher, fridge)$1,500 – $2,500$4,000 – $8,000
Backsplash tile & installation$600 – $1,200$1,500 – $3,000
Sink & faucet$300 – $600$800 – $2,000
Kitchen subtotal$9,200 – $13,600$19,800 – $37,000
The sweet spot for rental ADUs: Prefab cabinets from Home Depot's Hampton Bay line ($2,500–$3,000) paired with a 2cm quartz countertop ($1,800–$2,200 installed) and assembly labor ($2,500–$3,000) gives you a clean, modern kitchen that photographs well and holds up to tenant use — for about $8,000–$9,000 total. This is the configuration Skyline recommends for investment-focused ADUs.

Bathroom

ItemBudget (Rental Grade)Premium
Shower tile & installation$1,200 – $2,000$3,000 – $6,000
Vanity (36" with sink)$400 – $700$1,200 – $3,000
Toilet$200 – $350$500 – $1,200
Shower fixtures & hardware$400 – $800$1,500 – $4,000
Floor tile & installation$600 – $1,000$1,500 – $3,000
Mirror & accessories$150 – $300$400 – $1,000
Bathroom subtotal$2,950 – $5,150$8,100 – $18,200
Smart layout tip: In a 2-bedroom ADU, placing the second bathroom adjacent to the laundry room allows both spaces to share a single plumbing stack — saving $2,000–$4,000 in rough plumbing costs and reducing the risk of future leaks. This is a standard Skyline design practice that most homeowners never think to ask about.

7. Utility Connections: The Line Item That Surprises Everyone

Utility connections are consistently the most underestimated cost in ADU budgets. Many homeowners assume their existing service can simply be extended to the ADU — but LA County has specific requirements that often require significant upgrades.

UtilityTypical CostCommon Surprise
Water meter (new service)$3,000 – $6,000LADWP connection fees vary by zone
Sewer connection / lateral upgrade$4,000 – $10,000Old clay pipe may require full replacement
Electrical service upgrade (2-gang meter)$4,000 – $8,000LA County requires separate meter for ADU
Gas service extension$1,500 – $4,000SoCalGas connection + trenching
Solar interconnection (if applicable)$500 – $2,000NEM 3.0 may affect sizing
The 2-gang meter requirement is one of LA County's most expensive surprises. LA County requires ADUs to have a separate electrical meter from the main house. This means upgrading to a 2-gang meter panel — a process that requires SoCal Edison approval, a licensed electrician, and often a new service entrance. Budget $4,000–$8,000 for this alone. Skyline Builders anticipates this requirement on every project and includes it in the initial estimate.

8. Hidden Costs to Budget For

Beyond the line items above, there are several costs that experienced ADU builders know to budget for — but that rarely appear in a first-pass estimate from a less experienced contractor.

Hidden CostTypical RangeWhen It Hits
Temporary power during construction$800 – $1,500Before permanent service is connected
Porta-potty rental (4–6 months)$600 – $1,200Required by OSHA on active job sites
Dumpster / debris removal$1,500 – $3,000Multiple hauls during construction
Soil compaction testing$500 – $1,000Required before foundation pour
Special inspection fees$1,000 – $2,500Required for certain structural elements
Landscaping restoration$2,000 – $5,000Trenching for utilities damages yard
Furnishings (if renting furnished)$5,000 – $15,000Post-construction, optional
Property tax reassessment$1,200 – $3,600/yr ongoingADU adds assessed value

9. Financing & Grants: How to Pay for It

Most homeowners finance their ADU through one of four mechanisms. The right choice depends on your current equity, credit profile, and timeline.

Financing OptionTypical AmountRate (2026)Best For
Cash-out refinance$50K – $200K+6.5% – 7.5%High equity, long-term hold
HELOC (Home Equity Line)$50K – $150KPrime + 0.5–1%Phased construction draws
Construction-to-perm loan$100K – $300K7% – 8.5%New builds, converts to mortgage
CalHFA ADU GrantUp to $40,0000% (grant, not loan)Owner-occupants, income limits apply
Personal loan / unsecured$20K – $50K9% – 15%Garage conversions, smaller projects
The CalHFA ADU Grant Program provides up to $40,000 in forgivable grant funding to owner-occupants who build an ADU and commit to renting it at affordable rates for a defined period. Income limits apply, but many LA County homeowners qualify. Skyline Builders can connect you with a CalHFA-approved lender as part of our consultation process.

10. ROI: When Does It Pay Off?

At current LA County rental rates, a well-built ADU typically achieves full payback in 7–12 years — and then generates pure passive income for the life of the property. Here is how the math works for a typical Skyline project:

ScenarioAll-In CostMonthly RentAnnual IncomePayback Period
Garage conversion (400 sq ft, 1BR/1BA)$85,000$1,600 – $2,000$19,200 – $24,0004–5 years
Detached ADU (600 sq ft, 1BR/1BA)$165,000$2,200 – $2,800$26,400 – $33,6005–7 years
Detached ADU (800 sq ft, 2BR/2BA)$210,000$2,800 – $3,500$33,600 – $42,0005–7 years
Premium detached (1,000 sq ft, 2BR/2BA)$280,000$3,500 – $4,500$42,000 – $54,0006–8 years
Property value uplift adds to the ROI equation. LA County ADUs typically increase property value by 20–30% of the ADU construction cost in the first year. A $165,000 ADU may add $33,000–$50,000 in assessed value immediately — before you collect a single dollar of rent. This makes ADUs one of the highest-ROI home improvements available in California.

11. Red Flags in Contractor Bids

The LA ADU market has attracted a wave of contractors who are either inexperienced with the permitting process or deliberately lowballing to win the job. Here are the red flags that should make you walk away from any bid:

🚩 Bid under $100K for a detached ADU

Impossible at current LA labor and material costs without cutting corners or excluding permits.

🚩 No mention of permit fees in the estimate

Permits and plans are $8,000–$15,000. If they're not in the bid, you'll be surprised later.

🚩 No licensed architect or engineer on the team

LA County requires stamped drawings from a licensed professional. If they're skipping this, they're building without permits.

🚩 Asking for more than 10% upfront

California law limits deposits to 10% or $1,000, whichever is less, for home improvement contracts.

🚩 No mention of the 2-gang meter requirement

Any experienced LA ADU contractor knows about this. If they don't mention it, they haven't done many ADUs in LA County.

🚩 Vague timeline with no milestone schedule

A professional contractor provides a week-by-week schedule. Vague timelines are how projects drag from 6 months to 18 months.

12. Frequently Asked Questions

Can I build an ADU for under $100,000 in LA?

A Junior ADU (JADU) converting existing interior space can be done for $30,000–$75,000. A garage conversion can come in at $60,000–$110,000. But a new detached ADU with a foundation, full utilities, and separate meter will not be done properly for under $120,000 in LA County in 2026.

How long does the whole process take?

Plan to budget 12–18 months from first consultation to move-in. Plans and permits take 2–5 months depending on jurisdiction and project complexity. Construction takes 4–8 months. Skyline Builders' average timeline for a 600 sq ft detached ADU is 14 months from contract to keys.

Do I need to move out during construction?

No. ADU construction on a detached unit does not require you to vacate your main home. There will be noise, dust, and contractor activity on your property, but you can remain in residence throughout the build.

Will my property taxes go up?

Yes, but only on the value of the ADU — not the entire property. Under California's Prop 13 rules, only the new construction is reassessed. A $165,000 ADU might add $1,800–$2,200 per year in property taxes, which is easily offset by rental income.

Can I use the ADU for short-term rentals (Airbnb)?

LA City and most LA County jurisdictions allow short-term rentals only in owner-occupied properties, and only for the primary unit. ADUs are generally not permitted for short-term rental unless you live on-site. Always verify with your local jurisdiction before listing.

What's the best ADU layout for maximum rental income?

A 2-bedroom, 2-bathroom layout in 700–800 sq ft consistently commands the highest rent-per-square-foot in LA County. Placing the second bathroom adjacent to the laundry room saves on plumbing costs and improves livability. A private entrance, covered parking, and in-unit laundry are the three amenities that most increase rental value.